Project Milestones: | <$25M Days Needed: | ≥$25 <$50M Days Needed: |
≥$50M Days Needed: |
Requirement Received | 0 | 0 | 0 |
Market Research Documentation Completed | 7 | 7 | 7 |
Develop J&A, Acquisition Plan & RFO Approval | 21 | 21 | 21 |
J&A, Acquisition Plan, and RFQ Approval | 25 | 38 | 66 |
RFQ Issues | 7 | 7 | 7 |
Vendor Questions Due | 14 | 14 | 14 |
Technical Team Response to Vendor Questions Due to AQD | 3 | 3 | 3 |
Government Response to Vendor Questions and RFQ Amendment (if necessary) Issues to Vendors |
2 | 2 | 2 |
RFQ Closed and Offers Received | 14 | 14 | 14 |
TEP Vendor Clarification Questions to AQD | 5 | 5 | 5 |
Vendor Clarification Questions to Vendors | 2 | 2 | 2 |
Vendor Clarification Responses to AQD | 5 | 5 | 5 |
Technical Evaluations Completed | 14 | 14 | 14 |
Cost/Price Analysis Completed | 7 | 7 | 7 |
Discussions/Negotiations, If Necessary | 21 | 21 | 21 |
Final Quote Revisions Due, If Requested | 14 | 14 | 14 |
Final Evaluations, If Revisions Requested | 14 | 14 | 14 |
Source Selection Documentation Completed | 7 | 7 | 7 |
Contract Award and File Prepared | 14 | 14 | 14 |
Contract Award and File Reviewed (Including Legal) | 25 | 38 | 80 |
Contract Awarded | 3 | 3 | 3 |
Notice to Unsuccessful Offerors [FAR 8.405-2(d)] | 0 | 0 | 0 |
Request for Debriefings from Unsuccessful Offerors Due (3 days from notice) | 3 | 3 | 3 |
Protest Time Frame [FAR 33.103] (10 days after contract award or within 5 days after a debriefing date offered to the protestor under a timely debriefing request) | 7 | 7 | 7 |
Total Business Days: | 234 | 260 | 330 |