Procurement Action Lead Time Categories & Goals

IBC’s Acquisition Services Directorate establishes Procurement Action Lead Time goals based on dollar value and acquisition complexity.  

PALT is the approximate number of calendar days from the time the contracting officer accepts a complete acquisition package to the time of award.  An acceptable acquisition package includes:

  • Certified and approved Procurement Request or other funding document;
  • Complete independent government cost estimate;
  • Complete specifications and/or performance work statement, statement of work, statement of objectives;
  • Market Research documentation
Acquisition Category Goal to Award
(Calendar Days)
Large Acquisitions  
Competitive Contracts $150K - $10M 90 – 180
Competitive Contracts $10M - $50M 180 – 270
Competitive Contracts over $50M Up to 365
Sole Source Contracts $150K to $10M 90 – 150
Sole Source Contracts $10M to $50M 120 – 240
Sole Source Contracts over $50M Up to 270
SBIRs 45 – 120
Federal Supply Schedules / Government Wide Acquisition Contracts
Orders for Supplies 45 – 120
Orders for Services 60 – 180
AQD Indefinite Delivery Vehicles
Competitive Orders $0 to $10M 45 – 120
Competitive Orders over $10M 60 – 180
Sole Source Orders $0 to $700K 30 – 45
Sole Source Orders over $700K 60 – 90
Financial Assistance
Grants, Cooperative Agreements, Other Transaction Authority Up to 120
Small Purchases (Simplified Acquisition Procedures)
Purchases up to $25K 14 – 24
Purchases $25K to $150K 21 – 45
Commercial Purchases $150K to $7M 45 – 180
Modifications
Simple Modifications
(i.e. option exercise, administrative changes, etc.)
Up to 20
Complex Modifications
(i.e. constructive changes, claims, terminations, equitable adjustments, consideration, etc.)