Statement of Michael L. Connor, Commissioner
Bureau of
Reclamation
Before the
House Natural
Resources Committee
Subcommittee
on Water and Power
On
H.R. 2950
July 21, 2009
Madam Chairwoman and members of the Subcommittee, I am Mike Connor,
Commissioner of the Bureau of Reclamation.
Thank you for the opportunity to provide the Department of the
Interior’s views on H.R. 2950. The legislation
allows for prepayment of the current and future repayment contract obligations
of the Uintah Water Conservancy District (District) of the costs allocated to
their municipal and industrial water (M&I) supply on the Jensen Unit of the
Central Utah Project (CUP). H.R. 2950
would amend current law to change the date of repayment to 2019 from 2037. The legislation would also allow repayment to
be provided in several installments and requires that the repayment be adjusted
to conform to a final cost allocation.
The Department supports the goals of H.R. 2950. However, the legislation should be amended to
clarify that the early repayment will be of an amount equal to the net present
value of the foregone revenue stream. Under any repayment scenario, the Federal
Treasury must be made whole.
The District entered into a repayment contract dated June 3, 1976, in
which they agreed to repay all reimbursable costs associated with the Jensen
Unit of the CUP. However, pursuant to
Section 203(g) of the Central Utah Project Completion Act of 1992 (P.L. 102-575)
the District’s contract was amended in 1992 to reduce the project M&I
supply under repayment to 2,000 acre-feet annually and to temporarily fix repayment
for this supply based upon an interim allocation developed for an uncompleted
project. The 1992 contract required the
District to repay about $5.545 million through the year 2037 at the project
interest rate of 3.222% with annual payments of $226,585. The net present value of the amount remaining
from this income stream starting in 2009 is $3,887,364.[1]
However, the costs allocated to the contracted M&I supply, and the
M&I supply available through additional contract amendments, may be
significantly revised in the future upon project completion and Final Cost
Allocation. An additional currently unallocated cost of $7,419,513
is expected to be allocated to the contracted 2,000 acre-feet.[2] Assuming that the costs allocated to the contracted
2,000 acre-feet will be increased by $7,419,513 with the reallocation in 2019,
the net present value of the stream of benefits from this reallocation is $4,654,454. Therefore, under Reclamation’s assumptions, the
net present value of the total stream of benefits anticipated under this
contract is $4,654,454 plus $3,887,364, or $8,541,818. The
contracted M&I amount is $4.1 million and the adjustment amount is $7.4
million. In total non-discounted dollars,
the Conservancy District owes the Federal government $11.6 million.
Under Reclamation law, water districts are not
authorized to prepay their M&I repayment obligation based upon a discounted
value of their remaining annual payments.
This legislation would authorize early repayment by the Uintah
Conservancy District to the Federal government.
Because there is an interest component to the M&I repayment streams
to be repaid early, early repayment without an adjustment for interest would
result in lower overall repayment to the
The language in H.R. 2950 should be amended to clarify that this
legislation is requiring that the Federal government be paid what it is owed by
the Conservancy District. In supporting the concept of early repayment
of the amount owed under this contract, the
While the Department supports the goals of H.R.
2950, the legislation should be amended to clarify that the U.S. Treasury will
be repaid in full; our support depends upon language that will clearly
establish that early repayment under this legislation must be of an amount
equal to the net present value of the foregone revenue stream.
This concludes my testimony. I will be pleased to answer any questions the
Subcommittee may have.
[1] All net present value figures cited in this testimony were calculated by discounting the payment stream to the year 2009 using the rate from 30-year Treasury constant maturities for the week ending July 10, 2009. The exact net present value will fluctuate based on the date of the calculation and the Treasury rate.
[2] This allocation will be subject to revision should there be additions to the project.