Statement of J. William McDonald
Regional Director,
Bureau of Reclamation
Before the
Subcommittee on Fisheries, Wildlife, and Water
Committee on Environment and Public Works
My name is J. William McDonald, Regional
Director of the Pacific Northwest Region of the U.S. Bureau of
Reclamation. I am pleased to provide this progress report on
Reclamation’s implementation of actions to benefit
Reclamation has or shares responsibility for implementing over 60 of the 199 actions in the Reasonable and Prudent Alternative (RPA) in the National Marine Fisheries Service’s (NOAA Fisheries’) December 2000 Biological Opinion (FCRPS BiOp). This BiOp covers the continued operation and maintenance of the FCRPS and of Reclamation’s Columbia Basin Project, and the aggregate hydrologic effects on mainstem flows of the 19 Reclamation irrigation projects located in the Columbia River Basin (exclusive of the Snake River Basin above Hells Canyon).
Reclamation is generally on track in implementing those actions in the RPA which are our responsibility. Our hydro-electric generation efforts under the FCRPS BiOp include the operation of Grand Coulee and Hungry Horse Dams in a manner that assists in meeting certain flow targets and the annual acquisition of up to 427,000 acre feet of water in the Snake River Basin from willing participants to improve spring and summer streamflow conditions for juvenile fish migration.
Reclamation is on schedule on the implementation of the habitat restoration provisions of the RPA. As required by action 149 of the RPA, we have initiated programs in nine subbasins to assist with providing migration passage and screening on non-federal water diversion structures, and securing water and water rights from willing sellers and lessors for instream flows in accordance with state law. While Reclamation has the authority to plan and design fish screens and passage for non-federal water projects, we do not have the authority to fund construction. Thus, Reclamation’s ability to fully accomplish this work will be hampered unless we receive the statutory authority to construct, or provide financial assistance to others to construct, fish passage and screening on non-federally owned diversion structures beginning with fiscal year 2004.
In this regard, the
Administration, in an
Following the
We are also implementing research, monitoring, and evaluation (RM&E) activities, primarily in priority subbasins. This is important for determining the effectiveness of our actions and the status of the listed fish.
Reclamation has received sufficient appropriations to date to fund actions required in the FCRPS BiOp. Our appropriation for the Columbia/Snake Salmon Recovery Program has risen from $5.6 million in FY2001 to $15 million in FY2003. The President’s proposed level of funding is $19 million for FY2004. Most of this increase is needed to fund our off-site habitat improvements (i.e., passage and screening on non-federal water projects) in the tributary subbasins, and assumes enactment of legislation to provide the necessary authority. We appreciate your continued support of these efforts.
In conclusion, we are pleased with our progress to date in implementing the actions in the FCRPS BiOp for which we are responsible. At the same time, we are mindful of the importance and magnitude of the task which lies before us.