In
order to submit a Change Request (CR), you will need to download the Change
Request Form in PDF file format, complete the form and print it. You
need to have Acrobat Reader installed (Click here
to download Acrobat Reader) to view and complete the form.
Once you have
downloaded the form, please fill out “Requestor Information” and the
“Change Request Information” and then work through the Change Request
Process to obtain the appropriate approvals
Click
here to download the Change Request Process.
*NOTE: The requestor is responsible for completing ONLY the Requestor
and CR Information sections. All fields MUST be filled out completely.
Should the CR be approved, the FBMS PMO will be responsible for
completing the Proposed Cost Estimates section of the form, and the
Bureau Functional Owner associated with the CR will complete the
Funding Information portion.
Please
refer to the following instructions to complete the CR Form:
REQUESTOR
INFORMATION
Name: Enter the requestor’s
name
Agency: Enter the requestor’s
Agency or Office
Email: Enter the requestor’s
email address
Phone: Enter the requestor’s
work phone number
CHANGE REQUEST
INFORMATION
Application: The DOI Change
Request (CR) Form uses the official names of DOI systems to
catalogue and evaluate potential changes.
Priority: Indicate the
priority level by selecting low, medium or high.
Category: This list
contains the type or Category of the change requested.
Justification: Enter a brief
summary explaining the reason for your CR.
Description of Change: Describe in
detail the change you are requesting.
Planned Start/End
Date: Enter a start and end date for implementing the CR.
Reviewer Roles and Functions:
Bureau Functional Owner Reviews and
Approves/Disapproves CR: At this decision point, the
Bureau Functional Owner will have to approve any new CR's before they get sent to the Bureau System Owner.
At the start of the CR process, the Bureau Functional
Owner will receive each and every CR that has been completed and
associated with the system(s). They are expected to review the CR to
determine if it is an acceptable request for that system.
Bureau System Owner Reviews and
Approves/Disapproves CR: At this decision point, the
Bureau System Owner receives the CR that has been approved by the
Bureau Functional Owner. The Bureau System Owner is responsible
for reviewing and approving/disapproving the change as an acceptable
modification for the system. Specifically, the Bureau System
Owner should assess whether the change request has a negative and
unacceptable impact on the costs, performance, and mission intent of
the system in focus. If the Bureau System Owner finds the CR
acceptable, then the acceptance form is signed and the CR is routed to
the Bureau CIO.
Bureau CIO Reviews and
Approves/Disapproves CR:At this decision point, the Bureau CIO receives the CR that has
been approved by the Bureau System Owner.The Bureau System Owner is
responsible for ensuring that only quality and necessary change
requests are routed for the Bureau CIO’s review.Bureau CIO is expected to review the
content of the change request in order to determine if it is
satisfactory for the system and more importantly if it is satisfactory
given the overall technology and applications environment of the
Bureau.If the CIO finds the CR
acceptable, then the acceptance form is signed and the CR is routed to
CTOC Co-Chairs.
CTOC Reviews and
Approves/Disapproves Technical Changes in Change Request: At
this decision point, the CTOC chair is expected to review the content
of the request primarily to determine if it aligns with the approved
DOI technology architecture that is embodied in the current version of
the DOI Technical Reference Model (TRM).The TRM may be viewed at www.doi.gov/ocio/architecture.In addition, if the change request
may impact other departmental/bureau systems from an infrastructure
perspective, these should be assessed also.If additional information is
required from the initiator in conducting the review, the CTOC
representatives may contact the CR initiator for further information.
If the CTOC finds the CR acceptable, then the
acceptance form is signed and the CR is routed to the FBMS PMO.
FBMS PMO Determines if Change is
Acceptable: At this decision point the FMBS PMO
analyzes the functional and technical changes proposed in the request
and determines if those requests are acceptable to the FBMS project.
Specifically, the FBMS PMO would be analyzing their own project plan
and target architecture and determining whether the changes are
acceptable. If the FBMS PMO finds the change request acceptable,
then the acceptance is signed in the CR Form. If the CR will pose
a schedule and cost impact to the FBMS project, then the FBMS PMO will
enter their specific cost and time impacts. In order to minimize
uncontrolled costs to the FBMS project, costs associated with the CR
that impact the FBMS solution will be born by the requesting
bureau/office.
FBMS PMO Determines Cost and Time
Impacts: At this decision point, the FBMS PMO
details any cost and time impacts that the CR will have on the FBMS
solution. Specifically, the FBMS PMO will determine the extra costs
and delays that will result from the CR, and the FBMS PMO will document
those costs and delays in the CR Form and the CR is routed back to the
Bureau System Owner for approval. The Bureau System Owner
associated with the CR can either provide the required funds or cancel
the CR. If the FBMS PMO does not determine cost and time impacts,
then the results are logged in the CR Form and the CR is officially
accepted. Upon acceptance of the CR, notifications of the
acceptance should be sent to the CR Initiator, the Bureau Functional
Owner, the Bureau System Owner, the CTOC, and the Bureau CIO.
Bureau System Owner Determines
Funding Codes for CR: At this decision point, the
Bureau System Owner associated with the CR receives the cost and timing
impacts from the FBMS PMO and evaluates whether there are available
funds to perform the CR, and fund the associated changes in the FBMS
solution. This step is necessary to effectively manage schedule
and cost impacts to target enterprise solutions. Specifically,
the Bureau System Owner will be evaluating the new cost versus the
benefits of implementing the CR. Funding codes are required in
order to ensure that total funds are available (for the total cost
impact) prior to the CR being approved and implemented. If the
Bureau System Owner wishes to proceed and has available funds, the
funding codes are entered into the CR Form.Upon acceptance of the CR,
notifications of the acceptance should be sent to the CR Initiator, the
Bureau Functional Owner, the FBMS PMO, the CTOC, and the Bureau CIO.