New Snack Bar Near Completion
Have you noticed some new construction in the main corridor on the 4th floor? That is the future home of the new snack bar that will provide additional food services for the occupants of the Main Interior Building while the cafeteria is closed for modernization. The snack bar will be open for service the middle of May and will provide a variety of healthy food choices for occupants. Watch for updates on menu selections and opening dates.
Back to Top 
Construction Update
Floors 7-4:
final cleaning
Floors 3-1:
painting, carpet and ceramic tile installation, cleaning
Stairs 40/41/42/43:
stripping stairs (night work) painting steps
Credit Union: final inspection
North Penthouse: inspections
Snack Bar: May 15, 2008
CLOSINGS: Cafeteria: May 30, 2008
TOURS: Contact Junior Logan (202) 501-8602
Back to Top 
"Behind the Barriers" is on the Move
The Behind the Barriers posters that keep you informed of construction activities on each floor of the building during the modernization are being moved to new locations. In an effort to reduce the use of easels in the main corridors, the posters will be moved from the original locations of the basement and cafeteria and E and C Street entrances to the bronze Directory exhibit cases located throughout the building. Initial postings will be at the C and E Street entrances, and in the three panel glass information board just outside the gym entrance.
Back to Top 
SAFETY ALERT
Occupants touring space in the construction zone must be accompanied by an member of the Modernization Program Office Team.
Back to Top 
Insuring Occupant Safety
GSA conducted a blast mitigation assessment of the existing window systems in the Main Interior Building to determine the mitigation enhancement necessary to afford a predetermined level of protection. The assessment was conducted as a result of the Main Interior Building being identified as a Level IV Facility in the Department of Justice’s report on Vulnerability Assessment of Federal Facilities. Level Four Facilities include facilities with over 450 federal employees, more than 150,000 sq ft. and a high volume of traffic. The assessment identified window upgrade options and included studies on historic preservation, environmental aspects and energy considerations. Stop by the MPO office to see mockups.
Back to Top 
Modernization Program Office
Welcomes Administrative Assistant
Bridget Hooper, is the new person on the block and we hope you will join us in welcoming her on board! She has a great personality and is the first person you see as you enter the Modernization Program Office in the Main Interior building.
Back to Top 
Barriers Coming Down
By now you might have noticed that the hallways in the Main Interior building appear to be larger than in the past. You are absolutely right! As the construction nears completion, the hallway barriers are being removed. Construction temporary lighting will remain in the hallways for a while longer, as will the barriers protecting the murals. But, as we get closer to the April 30 completion date, the main corridors will once again reflect the openness of the past.
Back to Top 
What's that Noise?
As we get closer to the completion of the construction, we have had a number of complaints regarding increased noise during work hours. The good is that the construction team is now working in areas closest to the occupied space and we are nearing completion of the project. The bad is that not all work can be accomplished between 6:00 and 8:00 am in the morning. The Modernization Program Office is working with GSA and the contractors to keep the noise to a minimum and keep the project on schedule. In the mean time, we appreciate you patience!
Back to Top 
Plant Watchers get Ready!
With the move date nearing, everyone with plants in their office should either make plans to take them home or find a friend to keep them for a while!