New plans for 'negative air pressure'

Top left, negative air machines run in the west side of Wing 5. Above right, a Magnahelic gauge measures air pressure. In the coming weeks, each side of all floors will have these machines and gauges working inside an airlock buffer zone adjacent to occupied spaces.
During the Modernization Program Office
Listening Session, held on June 26, 2007, a key
concern voiced by attendees was the project’s inability
to establish and maintain negative air pressure
throughout the construction zone. Achieving negative
air pressure was also a key recommendation in the May
24, 2007, NIOSH report to DOI.
Negative air pressure refers to a pressure
differential between occupied space and the
construction zone. It is optimal to have air migrating
from occupied space into the construction zone in order
to inhibit dust, odors, and other possible irritants from
migrating from the construction zone into occupied
office space.
Previous efforts to establish negative air pressure
fell short because windows in the construction zone
were removed all at once, and the high-powered fans
failed to draw enough air to create the differential
In an a attempt to resolve this issues, the
modernization team recently built a mock-up of a
secondary barrier to be installed behind the established
barriers, to create a negative air space adjacent to
occupied space.
This barrier will create a “negative air pressure
zone” which will significantly reduce the opportunity
for air migration between the occupied space and the
construction zone.
Negative Pressure is only one step to increasing
barrier protection, strict compliance to the Sheet Metal
and Air Conditioning Contractors of North America
(SMACNA) guidelines is the other.
The barriers will be built on both sides of the
barrier on each floor of the construction zone in the
coming weeks. Pressure gauges, supplied by GSA, will
be mounted on each barrier on each floor, and will be
checked by GSA daily.
This measure, along with others already in place,
will substantially reduce odors, dust, and other indoor
air quality concerns.
However, one significant challenge remains. The
Mechanical Floor, located between Floors 5 and 6, is
dedicated to housing HVAC, electrical, mechanical, and
telecommunications equipment for the building. By its
very nature, it contains numerous penetrations that
allow these systems to service the building. These
penetrations make the possibility of negative air
pressure extremely challenging. A mechanical engineer
has been asked to review and analyze the space
configuration for possible solutions.
In the meantime, all construction activities on the
M-Floor are being contained in the construction zone,
and all doors have been sealed with two layers of
polyurethane and taping. Strict compliance with
SMACNA guidelines is being enforced in this area.
This curb will soon contain a re-introduced historic skylight above the MIB gymnasium.
Back to Top 
Beyond 'negative air':
Measuring SMACNA compliance
Beginning in early July, the Modernization Program Office has been issuing
and posting a
notice called “Behind the Barricade: Plan of the Week.”
This notice lists construction activities by floor and a percentage
rate of compliance with
the SMACNA IAQ Guidelines for Occupied Buildings Under Construction. While
this is the first
time a percentage was published, the checklist and corresponding inspections
have been occurring
regularly for a few weeks.
It must be noted that an industry standard for compliance with these guidelines
does not
exist. Therefore, the modernization team created a project-specific checklist
with a weighted
point system that would be used as an internal performance metric. From now
on, 90% to 100%
compliance will be coded “green”, 80%
to 89% compliance will be coded “yellow”, and below
79% will be coded “red”. The first week’s percentage was
81%.
A key component of SMACNA compliance is achieving negative air pressure.
However,
there is a multitude of practices large and small that must be adhered to
in order to reduce
indoor air quality concerns.
GSA and its contractor have been working diligently to create negative air
pressure (see previous
article) as well as maintain effective environmental controls.
The program expects the
compliance percentage to increase and for indoor air quality concerns to
be minimal in the near
future.
The notice and score are posted at C and E Street entrances, in the cafeteria,
and on the
modernization website: www.doi.gov/modernization. Please contact the MPO
if you would like
hard copies.
This curb will soon contain a re-introduced historic skylight above the MIB gymnasium.
Back to Top 
Staff Updates
The Modernization Program
Office will have a new program
manager reporting for duty in
mid-August. Additionally, a Deputy
Program Manager, an interdisciplinary
engineer, is being hired to assist with
adherence to contract specifications
and historical preservation obligations.
The office will also hire an industrial
hygienist and a safety manager in the
coming weeks under a proposed
realignment from facilities
management.
These new staff members will be
working with Gay Bindocci,
Sustainability Coordinator, and Junior
Logan, Telecommunications
Coordinator, with representing the
department's interests as the project
nears the half-way point for
completion. We ask that you get to
know the new staff as they arrive and
help them to ensure that the
department makes the most of this
historic opportunity to build a better
workplace.
Thanks to Ian Rosenblum, the
building's industrial hygienist, who has
accepted a promotional opportunity.
Ian's efforts helped to maintain safety
standards and to test and track the
building's environmental state.
This curb will soon contain a re-introduced historic skylight above the MIB gymnasium.
Back to Top 
Meetings
For more information regarding the IAQ Forums and the TUG meetings, click here.
This curb will soon contain a re-introduced historic skylight above the MIB gymnasium.
Back to Top 
|